For effective cost control, what specific project structure must a detailed Cost Breakdown Structure (CBS) always align with?



For effective cost control, a detailed Cost Breakdown Structure (CBS) must always align with the Work Breakdown Structure (WBS). The Work Breakdown Structure is a hierarchical decomposition of the total scope of work that needs to be accomplished to achieve project objectives and create deliverables. It breaks down the project into progressively smaller, more manageable components, starting from major deliverables and ending with specific work packages, which are the lowest level of the WBS and represent the work at which cost and schedule can be reliably estimated and managed. This structure defines *whatwork will be done in the project. A Cost Breakdown Structure, conversely, is a hierarchical categorization of all project costs, detailing where ....

Log in to view the answer



Community Answers

Sign in to open profiles and full community answers.

No community answers yet. Be the first to submit one.

Redundant Elements