Govur University Logo
--> --> --> -->
...

What is the primary function of a choke manifold during a well control event?



The primary function of a choke manifold during a well control event is to safely and precisely control the backpressure exerted on the wellbore while circulating out an influx (kick). A choke manifold is a system of high-pressure valves and chokes connected to the kill line and choke line of the Blowout Preventer (BOP) stack. During a well control event, an influx of formation fluids (gas, oil, or water) enters the wellbore, increasing the wellbore pressure. The choke manifold allows the....

Log in to view the answer



Redundant Elements