Govur University Logo
--> --> --> -->
...

When using the Critical Path Method (CPM), what is the definition of 'float' regarding a project activity that is not on the critical path?



In the Critical Path Method, float, also known as slack, is the amount of time that a project activity can be delayed from its early start date without delaying the project finish date. The critical path is the sequence of tasks that determines the shortest possible duration of a project; any delay to a task on this path directly delays the en....

Log in to view the answer



Redundant Elements