Govur University Logo
--> --> --> -->
...

When managing change orders, why is it necessary to evaluate the impact on the 'critical path' rather than just the construction budget?



The critical path is the sequence of project tasks that determines the shortest possible time to complete a project. If any task on this path is delayed, the entire project completion date is pushed back. When a change order—a formal document outlining a modification to the original scope of work—is introduced, focusing solely on the construction budget ignores time-related costs. A change order that adds ev....

Log in to view the answer



Redundant Elements